Decorative cover
Screws
Pipe 1
Pipe 2
Screw
Bolt
Nut
Water Inlet Pipe
Hole size on ceiling
1.
Drawing the line on the ceiling according to above specification
Decorative Cover
Pipe 1
2.
Connect pipe 1 with decorative cover
3.
Drill the holes on the ceiling according to above hole specification and install 4 pipes.
4.
According right drawing, install four-pipe 2 into pipe 1. Put the screw bolts through the hole on the side to lock pipe 2 with pipe 1.
5.
As the right drawing shown, install four-pipe 2 on the head shower.
6.
After fixing the showerhead on the ceiling, connect the shower hose with 2 water inlet on the showerhead back cover. The other end connect with the water outlet pipe in the wall.
5. As the right drawing is shown, install four-pipe 2 on the head shower.
6.
After fixing the showerhead on the ceiling, connect the shower hose with 4 water inlet on the showerhead back cover. The other end connects with the water outlet pipe in the wall.
Remarks: Ceiling mounted shower head come with fixing bar installation
1. Draw size on ceiling
2. Install fixing bar on ceiling
3. Install fixing bar on shower head
4. Put shower head bar on ceiling fixing bar.
The showerhead installation is now complete.
Hand-Held Shower Instructions
5. HOLE LOCATIONS FOR WALL MOUNT
Remove Front Cover (5A) from Wall Mount (5B). Use Wall Mount Screw Holes (5C) to place the desired location. Using a punch or awl, tap the screw hole locations.
Holes must be vertically aligned.
6. ANCHOR INSTALLATION
Drill two 1/4 dia. Holes (6A). If installing into a studs drill two 1/8 dia. holes and do not use Anchors (6B). Insert Anchors (6B) into Holes (6A) and tap flush with the wall.
7. WALL MOUNT INSTALLATION
Place Wall Mount (7A) into wall and inset Mounting Screws (7B) through Wall Mount Holes (7C) and tighten until Wall Mount (7A) is flush with the wall.
Do Not Over Tighten! Insert Front Cover (7D) into Wall Mount (7A)
8. DROP ELBOW & HOSE INSTALLATION
Apply PTFE plumbers tape on both ends of Pipe Nipple (8A) (not included). Screw Pipe Nipple (8A) into the elbow inside the wall.
The Pipe Nipple (8A) is to project 1/4 3/4 from the finished wall. Screw Drop Elbow (8B) onto Pipe Nipple (8A) and tighten until Drop Elbow (8B) is
property positioned and flush to the finished wall.
Place Rubber Seal (8C) inside Hex Hose Fitting (8D). Connect Hex Hose Fitting (8D) into Drop Elbow Outlet (8E) by turning Hex Hose Fitting (8D).
9. UNIT STARTUP
Turn on hot and cold water supplies, and check all connections for leaks.
10. FINAL FLUSHING
For final flushing, turn the valve on and allow water to run through the Hose (10A) for several minutes.
Allow water to run for several minutes until all foreign matter clears the line.
11. SHOWER ARM INSTALLATION
Place Rubber Seal (11A) inside Tapered Hose Fitting (11B). Conned Hand Shower (11C) to Hose (11D) by turning Tapered Hose Fitting (118) clockwise.
Shower Body Jets Installation
Multiple Bodyspray Installation
Water Supply
Nipple Mamelon Nipple
Pressure Balancing Loop
1. Route the water supply lines.
2. If installing more than one bodyspray off the same supply line, construct a pressure balancing loop. Locate a tee along the loop at each bodyspray installation location.
3. Do not strap the pipes at this time.
Single Bodyspray Installation
Nipple Mamelon Nipple
1. Route the water supply line.
2. Install an elbow to the end of the supply pipe at the bodyspray installation location.
Install the Plaster Guard
Elbow (or Tee)
Install the plaster guard
Set Piping Depth
Align mark with front of the stud face
Thin Wall
Align mark with front of the stud face
Standard Wall
Install the plaster guard. Push until the plaster guard is snug against the face of the elbow (or tee).
1. Install the water-resistant wall board.
2. Cut out a 4" (10.2 cm) to 4-1/4" (10.8 cm) square at each the installation location.
3. Install the finished wall material.
Escutcheon
Leak Shield
Adapter
Extension
Socket Wrench With Bit